ADVICE OF WORKS - FEBRUARY 2022

Published on Wednesday, 19 January 2022 at 1:56:24 PM

The Shire of Donnybrook Balingup advises that the following works are in progress or programmed to commence in the near future. Please note all works are subject to weather and other conditions, therefore dates may change.

 

SOUTHAMPTON ROAD – Road reconstruction and widening works between SLK 0.7 to SLK 2.0 will continue in February 2022.

UPPER CAPEL ROAD – Reconstruction and widening of road and improvements to existing drainage from SLK 11.9 to SLK 13 commenced in late January 2022 and will continue throughout February 2022.

SANDHILLS ROAD – Reconditioning of shoulders and drains will continue in February 2022.

COLLINS STREET – Road renewal works will commence in late January between SLK 0.2 and SLK 1.00 and continue throughout February 2022. These works will include sections of road being reconstructed, drainage infrastructure upgrades and renewal to concrete footpaths and kerbing.

Hours of operation are normally between 7.00 am and 5.00 pm, Monday to Friday. Works will be clearly signed and you are requested to exercise due care when travelling near or through these areas. Delays are expected to be minimal. 

 

Should you require further information, please contact the Shire Works & Services Department on 9780 4209.

 