The Shire of Donnybrook Balingup advises that the following works are in progress or programmed to commence in the near future. Please note all works are subject to weather conditions, therefore dates may change.

 

NEWLANDS ROAD, NEWLANDS – Sealing from end of existing seal for approximately 1 kilometre.
Works have commenced and will continue into December 2019.

KING SPRING ROAD, THOMSON BROOK – Sealing 220m section of King Spring Road near 179 King Spring Road.
Work is scheduled to take place in December 2019.

IRISHTOWN ROAD, DONNYBROOK – Pruning road-side vegetation and shoulder renewal works.
Works have commenced and will continue into December 2019.

DONNYBROOK TOWNSITE – Installation of Christmas lights.
Works to be completed be early December 2019.

UPPER CAPEL ROAD WORKS – Upgrading of the road to a 6.2m seal width.
Works are scheduled to commence from early January 2020. A detour via Ryalls Road will be in place for part of the works.

EGAN STREET, DONNYBROOK – Upgrade works between Allnutt and Marmion Street.
Works are scheduled to commence in early January 2020.

Hours of operation are normally between 7.00 am and 5.00 pm, Monday to Friday. Works will be clearly signed and you are requested to exercise due care when travelling near or through these areas.  Delays are expected to be minimal. 

Should you require further information, please contact the Shire Works & Services Department on 9780 4209.

 